Scope
1.1 This practice covers recommendations and identifies pertinent areas of consideration for the installation of buried geocomposite drains used for highway edgedrains, under-drains, or other pavement drainage applications. These recommendations are intended as guidelines for developing a satisfactory construction and installation method to minimize installation-caused deformation or damage and to provide long-term performance of these products. It is also intended as a guideline for ensuring a stable underground environment for these materials under a wide range of service conditions. Because of the numerous and diverse product designs available and the inherent variability of natural ground conditions, achieving satisfactory performance of any one product may require review by the engineer and modification to provisions contained herein to meet specific project requirements.
1.2 The scope of this practice necessarily excludes product performance criteria such as compressibility in any plane, flow capacity, inlet capacity, or geotextile selection and use. It is, therefore, incumbent upon the product manufacturer, specifier, and project engineer to verify that the product specified for an intended application, when installed according to procedures outlined in this practice, will provide satisfactory long term performance according to criteria established by the owner for that application. A commentary of product performance and installation factors important in achieving a satisfactory installation is included in Appendix X1.
1.3 The values stated in SI units are to be regarded as the standard. The inch-pound units given in parentheses are for information only.
1.4 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility of the user of this standard to establish appropriate safety and health practices and determine the applicability of regulatory limitations prior to use.
Keywords
backfill; "C"-ing; collector; conduit; drain positioning gate; edgedrain; geocomposites; geosynthetic; installation/placement boot; "J"-ing; joints; outlet pipe; outlet tees; trench; underdrain; wheel trencher; ICS Number Code 93.080.20 (Road construction materials)
To find similar documents by ASTM Volume:
04.09 (Soil and Rock (II): D5877 - latest)
To find similar documents by classification:
93.080.20 (Road construction materials Including asphalts, road pavements, etc.)
This document comes with our free Notification Service, good for the life of the document.
This document is available in either Paper or PDF format.
Document Number
ASTM-D6088-06R22
Revision Level
2006 R22 EDITION
Status
Current
Modification Type
Reapproval
Publication Date
May 10, 2022
Document Type
Practice
Page Count
9 pages
Committee Number
D35.03